On Track Project Update: August 19, 2024
East side of Harding Street interchange now closed: The entry/exit ramps on the east side of Harding Street at I-465 are now closed for up to 60 days (mid-October) for reconstruction work. For more information on ramp closures and detour for local traffic, click here. Lane restrictions: Reminders: Reminder:
On Track Project Update: August 12, 2024
🏁 NOW OPEN TO TRAFFIC 🏁 The new I-69/I-465 system interchange and the ramps at Epler Avenue are NOW OPEN to traffic! This milestone completes the connection of the 142-mile corridor from Evansville to Indianapolis, a project decades in the making! Thank you to all the I-69 Finish Line construction crews, consultants, and staff who made […]
On Track Project Update: August 6, 2024
On Tuesday, August 6, Gov. Eric J. Holcomb, 48th Vice President Mike Pence, 49th Gov. Mitch Daniels, and INDOT Commissioner Mike Smith were joined by members of the I-69 Finish Line project team and contracting partners, as well as federal, state and local officials for Connecting the Crossroads, an event held to mark the opening […]
On Track Project Update: July 29, 2024
The new system interchange at I-69 and I-465 is scheduled to open next month on the southwest side of Indianapolis, completing the interstate connection between southwest and central Indiana. Initial work began at the new interchange site in 2022 as part of the I-69 Finish Line project, which upgrades more than 26 miles of State […]
On Track Project Update: July 22, 2024
I-465 lane and ramp closures: Separate from the I-69 Finish Line project, lane and ramp closures are planned on I-465 northbound on the southeast side of Indianapolis through August 5. More information is available here. I-69 Traffic Updates:
On Track Project Update: July 15, 2024
I-465 lane and ramp closures: Separate from the I-69 Finish Line project, lane and ramp closures are planned on I-465 northbound on the southeast side of Indianapolis through August 5. More information is available here. I-69 Traffic Updates:
On Track Project Update: June 24, 2024
I-465 lane and ramp closures: I-69 Traffic Updates:
On Track Project Update: June 17, 2024
I-465 lane and ramp closures:
On Track Project Update: June 10, 2024
Exciting news! The flyover bridge that will eventually route millions of vehicles from I-69 northbound to I-465 westbound is a step closer to completion following a deck pour over the weekend. Once operational, it will significantly improve traffic flow. One of the largest within the new I-69/I-465 interchange, the bridge spans approximately 714 feet and […]
On Track Project Update: June 3, 2024
I-465 lane and ramp closures: Separate from the I-69 Finish Line project, lane and ramp closures are planned on I-465 southbound on the southeast side of Indianapolis until the end of June. More information is available here. Lane Restrictions: