On Track Project Update: June 3, 2024

Share

I-465 lane and ramp closures:

  • Starting at 7 p.m. on Friday, June 7, through 6 a.m. on Monday, June 10, expect a double right-lane closure on westbound I-465 between I-65 and Kentucky Avenue/SR 67. This double-lane closure is needed for work on overhead signs, paving, and bridge demolition. This single-lane condition is expected to cause delays on westbound I-465 throughout the weekend. Seek an alternative route to avoid travel delays.
  • On-ramps to westbound I-465 also expected to close as part of this work
    • Northbound US 31/East Street to westbound I-465 will be closed, Friday, June 7, to Monday, June 10.
    • Harding Street to westbound I-465 will be closed, Friday, June 7, to Monday, June 10.
    • The southbound US 31/East Street ramp to I-465 westbound will remain closed into summer.
  • On Monday, June 10, through Sunday, June 16, expect a daytime and nighttime single-lane closure on westbound I-465 from I-65 to US 31/East Street for paving and bridge work.
  • On Monday, June 10, from 9 p.m. to 6 a.m., a single-lane closure and intermittent 20-minute stops are expected on westbound I-465 between Kentucky Avenue/SR 67 and I-70 for removal of overhead signs.
  • On or after Friday, June 7, Harding Street under I-465 will be reduced to one through lane and one left-turn lane until August for overhead bridge work.

Separate from the I-69 Finish Line project, lane and ramp closures are planned on I-465 southbound on the southeast side of Indianapolis until the end of June. More information is available here.


Lane Restrictions:

  • On I-69 northbound, between Henderson Ford Road and Big Bend Road, daytime single lane restrictions are needed for side slope and shoulder repair work in Morgan County. 
  • During the next month, northbound and southbound SR 37 between Banta Road and Fairview Road may have intermittent daytime single-lane restrictions for pavement striping in Johnson County.
  • Expect daytime intermittent single-lane closures on northbound I-69 between Stotts Creek and  Perry Road on Monday, June 3, through Thursday, June 6, for rip rap installation.

Categories

The Latest Updates